SDR links nominal outside diameter to nominal wall thickness. It is essential for dimensional planning, but it does not by itself define the material, application or allowable pressure. This guide separates those concepts and shows how diameter, SDR, line speed and compound density translate into extrusion-line requirements.
What SDR Means
ISO 4065 defines the relationship between nominal outside diameter and nominal wall thickness for smooth-wall thermoplastic pipe. For a selected nominal size:
Here dn is nominal outside diameter and en is nominal wall thickness. Lower SDR means a thicker wall at the same outside diameter; higher SDR means a thinner wall.
Example: A 110 mm SDR 11 pipe has a nominal wall thickness of 10.0 mm. A 315 mm SDR 11 pipe has a nominal wall thickness of about 28.6 mm. Product standards apply preferred dimensions and minimum-wall rules, so final tooling values must come from the applicable dimension table.
PE100 Water Ratings at 20°C
The table below shows common PE100 water ratings using a minimum required strength of 10 MPa and an overall service coefficient of 1.25. It is a water-pressure reference, not a universal rating for gas, elevated temperature, aggressive fluids or every national standard.
| SDR | Nominal wall ratio | Typical PE100 water rating | Configuration implication |
|---|---|---|---|
| SDR 9 | dn/9 | PN 20 | High mass per metre and thermal load |
| SDR 11 | dn/11 | PN 16 | Thick-wall production |
| SDR 13.6 | dn/13.6 | PN 12.5 | Medium-to-thick wall |
| SDR 17 | dn/17 | PN 10 | Common medium-wall range |
| SDR 21 | dn/21 | PN 8 | Lower mass per metre |
| SDR 26 | dn/26 | PN 6.3 | Thin-wall process sensitivity increases |
Important: Application cannot be selected from SDR alone. Confirm the material designation, product standard, service coefficient, design temperature, fluid, surge/vacuum loads, installation method and local code.
From SDR to Required Output
Extruder capacity is driven by pipe mass per metre and line speed. For a solid-wall pipe, an engineering estimate is:
Use millimetres for diameter and wall thickness, and kg/m³ for density. Required output is mass per metre multiplied by line speed and 60. The examples below use 955 kg/m³ only for planning; replace it with the certified compound density and add an appropriate operating margin.
| Pipe | Nominal wall | Estimated mass | Example speed | Calculated output |
|---|---|---|---|---|
| 110 mm SDR 11 | 10.0 mm | 3.00 kg/m | 1.0 m/min | 180 kg/h |
| 110 mm SDR 17 | 6.5 mm | 2.02 kg/m | 1.0 m/min | 121 kg/h |
| 315 mm SDR 11 | 28.6 mm | 24.58 kg/m | 0.5 m/min | 737 kg/h |
| 315 mm SDR 17 | 18.5 mm | 16.46 kg/m | 0.5 m/min | 494 kg/h |
| 630 mm SDR 17 | 37.1 mm | 66.0 kg/m | 0.5 m/min | 1,980 kg/h |
Do not select an extruder from screw diameter or motor power alone. Compare guaranteed output on the specified compound, stable turndown, melt temperature, pressure capability, drive reserve and the head resistance of the actual tooling.
Die Head and Tooling
- Flow distribution: Choose a head that provides uniform residence time and circumferential flow at both minimum and maximum output.
- Tooling range: Confirm the mandrel and die set covers every diameter/SDR combination with a controllable annular gap.
- Die swell and drawdown: Determine them by compound-specific rheology and trial data; a fixed percentage is not reliable across lines.
- Thermal control: Zone layout and sensor placement must prevent cold bands, stagnation and local overheating.
- Co-extrusion: All load-bearing layers must meet the applicable material and product-standard requirements.
Calibration and Cooling Capacity
At a fixed outside diameter, the same calibrator may cover several SDRs, provided its operating range and the tooling design allow it. Cooling demand, however, rises strongly with wall thickness and throughput. Tank length alone is not a complete specification.
| Product example | Wall thickness | Relative thermal load | Commissioning focus |
|---|---|---|---|
| 110 mm SDR 21 | 5.2 mm | Lower | Avoid over-pulling and rapid surface freeze that hides internal heat. |
| 110 mm SDR 11 | 10.0 mm | Higher | Verify core cooling and dimension after full conditioning. |
| 315 mm SDR 17 | 18.5 mm | High | Balance spray coverage, water temperature and support. |
| 315 mm SDR 11 | 28.6 mm | Very high | Confirm total heat-removal capacity at guaranteed output. |
| 630 mm SDR 17 | 37.1 mm | Very high | Use thermal modelling and a full-output acceptance trial. |
Specify water-flow capacity, inlet temperature, heat-exchanger duty, spray coverage, tank vacuum stability, pipe support and guaranteed exit condition. Thicker walls often require multiple cooling stages, but their exact number and length must be calculated and validated.
Haul-Off, Cutting and Handling
Low-SDR pipe is heavier and may need more caterpillar contact area and drive torque, while thin-wall pipe is more sensitive to clamp deformation. Cutter selection must account for outside diameter, maximum wall, chip extraction, cut squareness and whether the pipe is rigid enough at the cutter. Downstream supports must prevent hot pipe from sagging or ovalizing.
Multi-Layer Pipe and SDR
SDR still refers to the total nominal wall geometry of the finished pipe. A co-extruded layer is not automatically structural. ISO 4427-2 includes certain co-extruded PE constructions where the layers have the same minimum required strength rating, but the exact layer design, thickness tolerance and test programme come from the applicable standard and approved product construction.
Changing Diameter or SDR
A changeover time cannot be guaranteed from SDR alone. It depends on whether the outside diameter changes, which tooling must be replaced, lifting and cleaning procedures, automation, material/colour change, and the required first-off tests.
| Change item | Typical dependency | Release check |
|---|---|---|
| Die/mandrel setting | Tooling design, gap range and centring method | Circumferential wall profile |
| Calibration sleeve | Outside-diameter change and sleeve operating range | Outside diameter and surface |
| Output and speed recipe | Mass per metre, cooling limit and extruder stability | Stable trend data |
| Haul-off and cutter | Diameter, wall, hot stiffness and cut method | Ovality and cut quality |
| Product approval | Applicable sampling and conditioning requirements | Required dimensional and laboratory results |
Quality Control
- Online wall measurement: Trend multiple circumferential points, but verify the system with calibrated offline instruments.
- Diameter and ovality: Measure at the conditioning state and locations required by the governing standard.
- Melt stability: Trend pressure, temperature, screw speed, output and haul-off speed together.
- Material traceability: Link every finished length to compound lot, line settings and inspection record.
- Acceptance tolerances: Use the dimensional tables in the applicable edition; do not apply a generic symmetrical percentage.
Configuration Checklist
| Component | Information required before sizing | Acceptance evidence |
|---|---|---|
| Extruder | Compound, diameter/SDR matrix, speed and output | Stable guaranteed throughput and melt quality |
| Die head | Tooling matrix, layer structure and operating range | Wall distribution and pressure stability |
| Vacuum sizing | Diameter range, surface requirement and vacuum demand | Diameter, ovality and surface finish |
| Cooling | Thermal load, utilities, ambient condition and exit limit | Full-output heat-removal test |
| Haul-off/cutter | Mass per metre, hot stiffness, diameter and wall | No slip/deformation and acceptable cut |
Primary References
Conclusion
Define the complete diameter, SDR, material, standard and target-speed matrix before ordering a line. Convert every product to mass per metre, calculate throughput, then size melt capacity, tooling, cooling, haul-off and cutting as one system. Require acceptance tests at the products that create the highest output, highest cooling load and greatest dimensional sensitivity.
Need a configuration recommendation?
Send the standard, compound, diameter/SDR matrix, target output, layer structure, utility conditions and required acceptance tests.
Contact the Engineering Team